CONTROVERSIAL plans for 29km of giant electricity pylons along the Essex-Suffolk border are back on the table.

The National Grid is reviving plans for new 400,000-volt power lines between Twinstead and Bramford, in Suffolk.

Plans were first unveiled in 2009 but were put on hold in November 2013.

Campaigners said the pylons would “decimate” the landscape and called for the powerlines to be buried underground instead.

The National Grid said: “We need to increase the network capability here to carry new clean green energy that is proposed in East Anglia.

“The proposed reinforcement is around 29km and includes building new pylons, some underground cables and a substation.

“We started the project in 2009 and carried out extensive public consultation.

“We paused work in November 2013 after timings of some generation projects in the region were delayed.

“Since then, the UK has made great leaps in moving towards cleaner, greener energy consumption.

“The Government has set ambitious targets to achieve net zero by 2050 and expected 4GW of electricity to be generated from offshore wind by 2030.

“These ambitions, coupled with increased demand for interconnection and new nuclear power, mean that generation in East Anglia is set to significantly increase.

“Our network studies show that we will need the reinforcement to be in place before the end of the decade and we now need to start work again to take forward the proposals.

“Over the coming weeks we will contact landowners to arrange access for surveys and we are preparing to start a non-statutory public consultation at the end of March.”

The previous plans earmarked Castle Hedingham as a possible site for the substation.

Hedingham councillor Jo Beavis said: “Having previously sat through the last non-statutory consultation and engagement events in Essex and Suffolk I understand only too well how concerned the residents I represent are. I understand the requirements to build a new 400,000 volt electricity reinforcement between Bramford substation and Twinstead, but my fears remain in two key areas.”

She says pylons could be a blight on the countryside and has fears over the logistics of building a substation in Castle Hedingham due to the narrow rural roads.

She added: “At this stage I have not had it confirmed that, as previously, Castle Hedingham will be proposed for the the substation but as I attended the previous meetings and Castle Hedingham has been asked to meet the project team, it seems it could be on the horizon again.”